此页面为我船舶测厚工作的一个时间记录,方便以后查询。

2024

5-7-5.14

OBS VENUS-HUAZI

IMO:9226750,LR,Build:2002.3.22

日期:YYYY-MM-DD

### 今日工作内容
– 任务1:描述
– 任务2:描述

### 问题记录
– 问题1:描述
– 解决方法:描述
– 问题2:描述
– 解决方法:描述

### 备注
– 其他重要信息

5.14:DBT 3P/S and finish

5.13:DBT 1P/S, 2P/S 4P/S 5P/S ADN UNDER DECK NO.2

5.12:BOTTOM PLATE  AND FPT

5.11:UNDER DECK 5,4,3,1

5.10:TST 1P, 2P ,APT , UPPER STOOL , LOWER STOOL

5.9:Inner bottom plate NO.1 ,TST 1-5S, 5P,4P,3P

remained TST 2P, 1P

5.8,Inner bottom plate NO.2-5

5.7,cargo hold sand blast, can’t check inner bottom plate

zhang want to know the inner bottom plate thickness measurement.

4.9-4.19

DREAM POWER-HuaFeng DaiShan-11 days

IMO:9515175,NK,12.5 intermediate survey

4.19,DBT3P/S have water, can’t check.

all finished.

4.18,FPT AND DBT 1S

4.17,CROSS DECK 1,4,5,7

4.15,DBT4S,2P/S,CROSS DECK 2,3

REMAIN : DBT 1S,3P/S , CROSS DECK 1,4,5,7 

4.13,DBT 1P,4p, all lower stool

4.12,overboard pipes and sea chest,APT

4.11,check Inner bottom plating and TST

all inner bottom plating

all TST

4.10,Borrowing drawings,check hatch coaming, hatch cover, deck

hatch coaming top plating need to repair.

inner bottom plate gauge , not sure is good or bad

4.9,办理入厂手续

completing the entry formalities for the shipyard

3.28-4.6

TRADE-RuiTai-7 days

3.28,看TST3P/S,2S,APT

3.30,check cross deck, DBT 1S

DBT1S,hopper plating have local corrosion

small bellmouth have corrosion

4.2,check DBT

1p,2s,3p/s,4s,5p

remain 2p,4p,5s

2p,5s have too much water.

all sounding pipes double web need change

bilge transverse web belding

4.3,check dbt2p,4p

dbt5s have water

4.4,check dbt5s, overboard pipes and sea chest

4.5,check bottom plating and FPT

4.6,check the welding on the bow of ship with ship supervisor

3.24,3.27

SEA STAR(海星)-瑞泰-2天

3.27,I WORK ALONE ON THE SHIP

CH2 INNER BOTTOM PLATING , FRAMES

CH1 INNER BOTTOM PLATING , SHIPYARD IS REPAIRING THE FRAME AND SHELL PLATING

CROSS DECK 

NO.1,2.3

TST1P

APT

SST AND FWWT

HATCH COVER

3.24,4个人一起,我早上跟着船检看了1STSP和FPT,下午我和彭看,我看DBT5S,3S,1P

3.20-3.26

OKIANA(奥卡娜)-澄西-6天

WORK FOR 6 DAYS ON THE SHIP

DNV CLASS , 

A TWENTY YEARS SHIP

SURVEY SCOPE:

1. three transverse sections

2. all main deck plating

3. all cargo hold hatch cover and coaming plating and stiffeners

4. wind and water strakes

5. Strakes of transverse bulkheads in cargo spaces together with internals in way

All bulkheads – lowest strake and strakes in way of ‘tween decks.

6. ALL bottom plating

7. sea chest and shell plating 

8. superstructure deck plating

9. apt and fpt

DAILY–MAJOR WORKING PROGRESS:

3.26,the sixth day on the ship in chengxi shipyard

WBT 4S,3S

CH 12,11,10 

3.25,the fifth day on the ship in chengxi shipyard

WBT 2P 3P

APT AND FPT

3.23,the fourth day in chengxi shipyard

Main deck

WBT 4P only aft DBT no chect

WBT 4S only DBT no chect

DBT 3P/S 

3.22,the thrid day in chengxi shipyard

CH BHD lowest strake NO.2,1

Hatch Cover NO.12,11,10,8,6

Superstructure

Overboard pipe and Sea Chest

3.21,the second day in chengxi shipyard

hatch coaming drawing finished

check CH BHD lowest strake NO.9,7,5

3.20,第一天,早上10点到澄西,办完证就11点多了。

办证,一个去的是厂门口7楼,修船部,另一个在码头哪里2楼。

中午上船,借图纸。

下午近观检查甲板及舱口围,整体状况还可以,像极了集装箱船的甲板结构。

3.5-3.8

VIENNA(维也纳)-瑞泰-4天

WORK FOR 4 DAYS ON THE SHIP

BV CLASS , SURNAME XI

A FIFTEEN YEAR SHIP

WORK ACCOMPLISHED:

DBT ALL TANK

TST ALL TANK

OVERBOARD PIPE

SUPERSTRUCTURE : A DECK , B DECK , C DECK , D DECK , NAV. BRI. DECK , COMP. DECK

TST ALL WITH SURVEYOR 

DAILY–MAJOR WORKING PROGRESS:

3.5,DBT 5P/S,4S , TST 1P/S

WE ARE ON THE SHIP AT 12 O’CLOCK.

WORKING PROGRESS:

CHECK DBT 5S AND 4S WITH WS, I CHECK DBT 5P AND TST 1P/S 

3.6,OVERBOARD PIPE

WE ARRIVED ON THE SHIP EARLY IN THE MORNING , DBT MUD CLEANING 

I FOUND THE DENTS IN SHELL PLATE , 5CH STDB , MAYBE ABOUT FR 40 

CHECK OVERBOARD PIPE , IT IS GOOD.

3.7,SUPERSTRUCTURE , TST ALL WITH SURVEYOR .

BECAUSE MY COLLEAGUE WS IS COMMON COLD , I GO TO SHIP ALONE .

HOW TO MAKE SURE FR ABOUT TST TRANSVERSE SECTIONS.

3.8,DBT ALL TANK WITH SURVEYOR

DBT WEB BEND AND CRACK IN DBT 1P 2P/S 3S 4P

UTM JOB ALL FINISH